USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Section 10 of the Rivers and Harbors Act of 1899: Publication of Public Notice (Agency Action)

Submitted by ian.slayton@boem.gov on

Triggered missed date from extending Publication of Public Notice (Agency Action) within 30 days of its current target date which was 09/30/2022 and extended to 01/26/2024

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Billy Standridge
POC Title:
Regulatory Project Manager

Description:

Department of Army authorization from the US Army Corps of Engineers Wilmington District is required pursuant to Section 10 of the Rivers and Harbors Act of 1899 (RHA).  Activities that require authorization include: Installation and scour protection of up to 60 wind turbines, one off-shore electrical service platform, installation of inter-array cables, and export cables from the Wind Development Area to the State Waters of Virginia (3nm from VA coast).

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Current Target Date:
Milestone Details

On April 6, 2021, the project sponsor indicated they are agreeable to submitting the initial permit application 30 days prior to BOEM's anticipated issuance of the draft EIS, which would be September 1, 2022.

Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Current Target Date:
Milestone Details

The Corps anticipates working closely with the sponsor to ensure the initial application contains all the items needed for a complete application. It is anticipated that any completeness items needed after the initial submittal will be received within 15 days of the initial submittal.

Publication of Public Notice (Agency Action)
Current Target Date:
Milestone Details

A public notice will be issued to coincide with BOEM's target date for publication of the Official Notice of Availability of a draft EIS in the Federal Register so long as the Corps has received a complete application by that date.

Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The Corps anticipates making a permit decision on or before November 1, 2023, 90 days after BOEM's target date of August 3, 2023 for Issuance of a Record of Decision.  However, this date will be subject to dependencies, including but not limited to conclusion of consultations pursuant to Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and the Magnuson-Stevens Fishery Conservation and Management Act.   

Finally, the district may require a mitigation plan compliant with the Corps/EPA 2008 Joint Mitigation Rule and information regarding alternatives from the project sponsor prior to rendering a permit decision.  Should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.

Milestone
Publication of Public Notice (Agency Action)
Current Target Date:
Milestone Details

A public notice will be issued to coincide with BOEM's target date for publication of the Official Notice of Availability of a draft EIS in the Federal Register so long as the Corps has received a complete application by that date.

Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

Update: In June 2022, the project name changed from Kitty Hawk Wind Project to Kitty Hawk North Wind Project to reflect the segmenting of the project.

The purpose of the Kitty Hawk North Wind Project is to develop a commercial-scale, offshore wind energy facility in Commercial Lease OCS-A 0508 offshore North Carolina, with up to 69 total wind turbine generators, 1 offshore substation (also called “electrical service platform”), inter-array cables, 1 onshore substation, and up to 2 transmission cables making landfall in Virginia Beach, Virginia, and connecting to the Pennsylvania-New Jersey-Maryland (PJM) Interconnection energy grid. Kitty Hawk is actively seeking one or more power purchase agreement awards for this project. The project is intended to substantially contribute to the region’s electrical reliability and help Virginia achieve its renewable energy goals as stated in the Virginia Clean Economy Act.

FAST-41 provides increased transparency and predictability by requiring Federal agencies to publish comprehensive permitting timetables for all "covered" projects, and provides clear procedures for modifying permitting timetables to address the unpredictability inherent in the environmental review and permitting process for significant infrastructure projects. For more information, see "The FAST-41 Process" at  https://www.permits.performance.gov/fpisc-content/fast-41-process

field_status
System Comments
Triggered missed date from extending Publication of Public Notice (Agency Action) within 30 days of its current target date which was 09/30/2022 and extended to 01/26/2024
Approver Comments
Action was in Dashboard prior to 8/30 (30 days) but was in Draft. Other milestones were shifted to Needs Review and this was an oversight that was corrected on 9/1. Exempted from nonconformance.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
Yes
New Milestone
Publication of Public Notice (Agency Action)
Current Target Date:
Milestone Details

A public notice will be issued to coincide with BOEM's target date for publication of the Official Notice of Availability of a draft EIS in the Federal Register so long as the Corps has received a complete application by that date.

Response Date