Permitting Action Modification History

Planned
The changes to the PDE will need to be analyzed and considered by USACE as part of their permitting processes. In addition, the Section 10/404 final completion date is dependent upon the final completion date of BOEM’s NEPA action. For this project, the USACE review will require 120 days between issuance of the ROD and issuance of USACE’s Section 10/404 decision. Therefore, an extension of the Section 10/404 final completion date is requested based upon the extension of the NEPA completion date.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-01-2022 06-11-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2022 06-26-2025 --- No
Publication of Public Notice (Agency Action) 09-30-2022 07-11-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 11-01-2023 09-15-2026 --- No
Planned
The USACE timetable is being updated to reflect BOEM's revisions to the EIS timetable.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-01-2022 03-27-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2022 04-11-2024 --- No
Publication of Public Notice (Agency Action) 09-30-2022 04-26-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) 11-01-2023 07-01-2025 --- No
Planned
The milestones are moving to align with a new permitting schedule due to changes in the timing of the MMPA permit submission.   9-7-2022 - CC Added Original Target Date Entry
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-01-2022 12-27-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 09-15-2022 01-11-2024 --- No
Publication of Public Notice (Agency Action) 09-30-2022 01-26-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) 11-01-2023 03-03-2025 --- No