USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Right-of-Way Authorization (DOI-BIA): Application deemed complete (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 07/31/2024 for Application deemed complete (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Indian Affairs
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Nilah Solomon
POC Title:
BIA Realty

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
  • Monthly Status Report for September 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. The ROW application has been approved by the Superintendent at the BIA Winnebago Agency, effective 6/23/25. Subsequently, BIA has received multiple appeals against that decision, with the most recent having been received on 8/12/25. Administrative records of appeal have been provided to the BIA Great Plains Regional Office for review. Responses to appeals are to be issued within 90 days, although regulations allow for an additional 90 days under some circumstances. BIA is in discussions with the project proponent and lead agency regarding the remaining milestone (Final Decision/Agency Action). In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to fulfil any remaining agency actions.
  • Monthly Status Report for August 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. BIA has prioritized appraisals with the Appraisal and Valuation Services Office to help expedite the project timeline to the maximum extent possible. An appeal was filed on 6/30/2025 by a beneficiary and sent to the BIA Great Plains Regional Office for review. Winnebago Agency is coordinating with the Great Plains Regional Office and providing an administrative record of the Winnebago Tribe's right-of-way. A response to the appeal will be issued within 90-days. The milestone ‘Application deemed complete (Agency Action)’ was marked completed on the Dashboard on 7/25/25. We anticipate the remaining milestone ‘Final decision (Agency Action)’ will be completed by 9/30/25, following the conclusion of the appeals process. In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to complete the application requirements.
  • Monthly Status Report for July 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. BIA has prioritized appraisals with the Appraisal and Valuation Services Office to help expedite the project timeline to the maximum extent possible. A decision letter was sent to landowners on 6/20/2025 informing of the approval of Winnebago Tribe of Nebraska right-of-way for fiber optic installation, with appeal rights due to close with finalization of the approved right-of-way on 7/23/2025. An appeal was filed on 6/30/2025 by a beneficiary and sent to the BIA Great Plains Regional Office. Winnebago Agency is coordinating with the Great Plains Regional Office and providing an administrative record of the Winnebago Tribe's right-of-way. A response to the appeal will be issued within 60-days. In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to complete the application requirements.
  • Monthly Status Report for June 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. BIA has prioritized appraisals with the Appraisal and Valuation Services Office to help expedite the timeline; appraisals are expected to be completed by July 3. An open comment period (required under the 'Too-Numerous' process) extends thru June 23, followed by a 30-day review/response period. BIA expects to be able to issue a determination for the project on July 23. In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to complete the application requirements.
  • Monthly Status Report for May 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. To date, the application remains incomplete. To complete the application package, BIA has requested additional documentation to sufficiently address 1) ‘just’ compensation; 2) eligibility as a Tribal utility; 3) consent for parcels the Tribe owns entirely; 4) insufficient consent for certain tracts; and 5) bonding. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe to complete the application requirements.
  • Monthly Status Report for April 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for March 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for February 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for January 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Monthly Status Report for December 2024:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for November 2024:
    The BIA cannot begin processing the project application until it is complete. Right-of-Way consent from allotment owners is needed before the application can be deemed complete. BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Monthly Status Report for October 2024:
    The BIA cannot begin processing the project application until it is complete. Right-of-Way consent from allotment owners is needed before the application can be deemed complete. BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Monthly Status Report for September 2024:
    The BIA cannot begin processing the project application until it is complete. Right-of-Way consent from allotment owners is needed before the application can be deemed complete. BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Non-conformance Explanation:
    The Winnebago Tribe and NTIA have been meeting at least weekly with BIA real estate to further understand all the requirements for crossing native allotment lands. Obtaining all the parcel and landowner information has been challenging with some mapping disagreements between BIA needs versus what the Winnebago Tribe can provide. The Winnebago Tribe is reviewing all the BIA routes and associated maps and will provide to the BIA Winnebago Agency, review ownership and maintenance responsibility and determine what documentation is available on the routes and determine if they have a ROW. Once determined who currently has a ROW, they can use it to assist in writing legal descriptions. Some surveys may still be needed depending on the results of the search. BIA originally asked for on-the-ground survey mapping of these parcels versus readily available Winnebago Tribe GIS data. However, the Winnebago Tribe and BIA are working to determine the acceptable level of documentation and description needed for the easements to keep the project moving forward and achieve the updated BIA ROW milestones
Alternative Completion Date:
Final decision/agency action (Agency Action)
Alternative Completion Date:
Milestone
Application deemed complete (Agency Action)
  • Monthly Status Report for September 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. The ROW application has been approved by the Superintendent at the BIA Winnebago Agency, effective 6/23/25. Subsequently, BIA has received multiple appeals against that decision, with the most recent having been received on 8/12/25. Administrative records of appeal have been provided to the BIA Great Plains Regional Office for review. Responses to appeals are to be issued within 90 days, although regulations allow for an additional 90 days under some circumstances. BIA is in discussions with the project proponent and lead agency regarding the remaining milestone (Final Decision/Agency Action). In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to fulfil any remaining agency actions.
  • Monthly Status Report for August 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. BIA has prioritized appraisals with the Appraisal and Valuation Services Office to help expedite the project timeline to the maximum extent possible. An appeal was filed on 6/30/2025 by a beneficiary and sent to the BIA Great Plains Regional Office for review. Winnebago Agency is coordinating with the Great Plains Regional Office and providing an administrative record of the Winnebago Tribe's right-of-way. A response to the appeal will be issued within 90-days. The milestone ‘Application deemed complete (Agency Action)’ was marked completed on the Dashboard on 7/25/25. We anticipate the remaining milestone ‘Final decision (Agency Action)’ will be completed by 9/30/25, following the conclusion of the appeals process. In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to complete the application requirements.
  • Monthly Status Report for July 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. BIA has prioritized appraisals with the Appraisal and Valuation Services Office to help expedite the project timeline to the maximum extent possible. A decision letter was sent to landowners on 6/20/2025 informing of the approval of Winnebago Tribe of Nebraska right-of-way for fiber optic installation, with appeal rights due to close with finalization of the approved right-of-way on 7/23/2025. An appeal was filed on 6/30/2025 by a beneficiary and sent to the BIA Great Plains Regional Office. Winnebago Agency is coordinating with the Great Plains Regional Office and providing an administrative record of the Winnebago Tribe's right-of-way. A response to the appeal will be issued within 60-days. In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to complete the application requirements.
  • Monthly Status Report for June 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. BIA has prioritized appraisals with the Appraisal and Valuation Services Office to help expedite the timeline; appraisals are expected to be completed by July 3. An open comment period (required under the 'Too-Numerous' process) extends thru June 23, followed by a 30-day review/response period. BIA expects to be able to issue a determination for the project on July 23. In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to complete the application requirements.
  • Monthly Status Report for May 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. To date, the application remains incomplete. To complete the application package, BIA has requested additional documentation to sufficiently address 1) ‘just’ compensation; 2) eligibility as a Tribal utility; 3) consent for parcels the Tribe owns entirely; 4) insufficient consent for certain tracts; and 5) bonding. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe to complete the application requirements.
  • Monthly Status Report for April 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for March 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for February 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for January 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Monthly Status Report for December 2024:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for November 2024:
    The BIA cannot begin processing the project application until it is complete. Right-of-Way consent from allotment owners is needed before the application can be deemed complete. BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Monthly Status Report for October 2024:
    The BIA cannot begin processing the project application until it is complete. Right-of-Way consent from allotment owners is needed before the application can be deemed complete. BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Monthly Status Report for September 2024:
    The BIA cannot begin processing the project application until it is complete. Right-of-Way consent from allotment owners is needed before the application can be deemed complete. BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Non-conformance Explanation:
    The Winnebago Tribe and NTIA have been meeting at least weekly with BIA real estate to further understand all the requirements for crossing native allotment lands. Obtaining all the parcel and landowner information has been challenging with some mapping disagreements between BIA needs versus what the Winnebago Tribe can provide. The Winnebago Tribe is reviewing all the BIA routes and associated maps and will provide to the BIA Winnebago Agency, review ownership and maintenance responsibility and determine what documentation is available on the routes and determine if they have a ROW. Once determined who currently has a ROW, they can use it to assist in writing legal descriptions. Some surveys may still be needed depending on the results of the search. BIA originally asked for on-the-ground survey mapping of these parcels versus readily available Winnebago Tribe GIS data. However, the Winnebago Tribe and BIA are working to determine the acceptable level of documentation and description needed for the easements to keep the project moving forward and achieve the updated BIA ROW milestones
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/14/2026

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Commerce

LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Section 408

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Bureau of Indian Affairs

Department of War Seal

Department of War, US Army Corps of Engineers - Regulatory

Description:

The project will construct a multi-conduit, underground Fiber to the Premises (FTTP) system, more than two hundred thirty-five (235) total miles, which will connect every household and business within the Winnebago Reservation. Eight hundred eighty-six (886) households and 46 businesses and organizations will have access to fiber bringing high-quality internet capability, including medical facilities and schools.  The fiber-optic installation alignment is generally located on the Winnebago Tribe of Nebraska Reservation, which spans approximately 120,000 acres and is situated primarily in a rural area in the northern half of Thurston County in northeast Nebraska, 20 miles south of Sioux City, Iowa, and 80 miles north of Omaha, Nebraska. U.S. highways 75 and 77 join in the east-central area of the reservation, near the community of Winnebago. A small portion of the reservation is located directly east of the Missouri River west of Interstate 29 in Woodbury County, Iowa.  

 

 

 

 

 

 

 

 

 

 

 

 

 

field_status
System Comments
Agency Milestone Date of 07/31/2024 for Application deemed complete (Agency Action) has passed by 1 business days
Approver Comments
<p style="margin-bottom:11px"><span style="font-size:12pt"><span style="line-height:115%"><span style="font-family:Aptos,sans-serif">Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials.&nbsp;</span></span></span><span style="font-size:12pt"><span style="line-height:115%"><span style="font-family:Aptos,sans-serif">The ROW application has been approved by the Superintendent at the BIA Winnebago Agency, effective 6/23/25. Subsequently, BIA has received multiple appeals against that decision, with the most recent having been received on 8/12/25. Administrative records of appeal have been provided to the BIA Great Plains Regional Office for review. Responses to appeals are to be issued within 90 days, although regulations allow for an additional 90 days under some circumstances.&nbsp;</span></span></span><span style="font-size:12pt"><span style="line-height:115%"><span style="font-family:Aptos,sans-serif">BIA is in discussions with the project proponent and lead agency regarding the remaining milestone (Final Decision/Agency Action). In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to fulfil any remaining agency actions. </span></span></span></p>
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
Agency Notified Date
New Milestone
Application deemed complete (Agency Action)
  • Monthly Status Report for September 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. The ROW application has been approved by the Superintendent at the BIA Winnebago Agency, effective 6/23/25. Subsequently, BIA has received multiple appeals against that decision, with the most recent having been received on 8/12/25. Administrative records of appeal have been provided to the BIA Great Plains Regional Office for review. Responses to appeals are to be issued within 90 days, although regulations allow for an additional 90 days under some circumstances. BIA is in discussions with the project proponent and lead agency regarding the remaining milestone (Final Decision/Agency Action). In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to fulfil any remaining agency actions.
  • Monthly Status Report for August 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. BIA has prioritized appraisals with the Appraisal and Valuation Services Office to help expedite the project timeline to the maximum extent possible. An appeal was filed on 6/30/2025 by a beneficiary and sent to the BIA Great Plains Regional Office for review. Winnebago Agency is coordinating with the Great Plains Regional Office and providing an administrative record of the Winnebago Tribe's right-of-way. A response to the appeal will be issued within 90-days. The milestone ‘Application deemed complete (Agency Action)’ was marked completed on the Dashboard on 7/25/25. We anticipate the remaining milestone ‘Final decision (Agency Action)’ will be completed by 9/30/25, following the conclusion of the appeals process. In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to complete the application requirements.
  • Monthly Status Report for July 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. BIA has prioritized appraisals with the Appraisal and Valuation Services Office to help expedite the project timeline to the maximum extent possible. A decision letter was sent to landowners on 6/20/2025 informing of the approval of Winnebago Tribe of Nebraska right-of-way for fiber optic installation, with appeal rights due to close with finalization of the approved right-of-way on 7/23/2025. An appeal was filed on 6/30/2025 by a beneficiary and sent to the BIA Great Plains Regional Office. Winnebago Agency is coordinating with the Great Plains Regional Office and providing an administrative record of the Winnebago Tribe's right-of-way. A response to the appeal will be issued within 60-days. In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to complete the application requirements.
  • Monthly Status Report for June 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. BIA has prioritized appraisals with the Appraisal and Valuation Services Office to help expedite the timeline; appraisals are expected to be completed by July 3. An open comment period (required under the 'Too-Numerous' process) extends thru June 23, followed by a 30-day review/response period. BIA expects to be able to issue a determination for the project on July 23. In the interim, BIA is providing technical assistance and coordinating closely (including weekly meetings) with the Tribe to complete the application requirements.
  • Monthly Status Report for May 2025:
    Bureau of Indian Affairs (BIA) has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. To honor that responsibility, due diligence must be exercised in the review of submitted right-of-way application materials. To date, the application remains incomplete. To complete the application package, BIA has requested additional documentation to sufficiently address 1) ‘just’ compensation; 2) eligibility as a Tribal utility; 3) consent for parcels the Tribe owns entirely; 4) insufficient consent for certain tracts; and 5) bonding. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe to complete the application requirements.
  • Monthly Status Report for April 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for March 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for February 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for January 2025:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Monthly Status Report for December 2024:
    The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it implements its process to seek allotment owner consent.
  • Monthly Status Report for November 2024:
    The BIA cannot begin processing the project application until it is complete. Right-of-Way consent from allotment owners is needed before the application can be deemed complete. BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Monthly Status Report for October 2024:
    The BIA cannot begin processing the project application until it is complete. Right-of-Way consent from allotment owners is needed before the application can be deemed complete. BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Monthly Status Report for September 2024:
    The BIA cannot begin processing the project application until it is complete. Right-of-Way consent from allotment owners is needed before the application can be deemed complete. BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
  • Non-conformance Explanation:
    The Winnebago Tribe and NTIA have been meeting at least weekly with BIA real estate to further understand all the requirements for crossing native allotment lands. Obtaining all the parcel and landowner information has been challenging with some mapping disagreements between BIA needs versus what the Winnebago Tribe can provide. The Winnebago Tribe is reviewing all the BIA routes and associated maps and will provide to the BIA Winnebago Agency, review ownership and maintenance responsibility and determine what documentation is available on the routes and determine if they have a ROW. Once determined who currently has a ROW, they can use it to assist in writing legal descriptions. Some surveys may still be needed depending on the results of the search. BIA originally asked for on-the-ground survey mapping of these parcels versus readily available Winnebago Tribe GIS data. However, the Winnebago Tribe and BIA are working to determine the acceptable level of documentation and description needed for the easements to keep the project moving forward and achieve the updated BIA ROW milestones
Current Target Date:
Response Date
Reporting Agency