USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
The BIA has a fiduciary and trust responsibility to both Tribes and individual Indian allotment owners. Right-of-Way consent from allotment owners is needed before the project application can be deemed complete. Once the application is complete, BIA can begin processing it. In the interim, BIA is providing technical assistance and coordinating closely with the Tribe as it plans its process to seek allotment owner consent.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-01-2024 07-01-2024 --- Yes
Application deemed complete (Agency Action) 07-31-2024 07-31-2024 04-30-2025 No
Final decision/agency action (Agency Action) 09-30-2024 09-30-2024 06-30-2025 No
Planned
The Winnebago Tribe, NTIA and BIA Great Plains and Winnebago Agencies worked together to come up with realistic ROW application dates given the amount of allotment lands being crossed. There is a large coordination effort involved that will take an additional six months. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-01-2024 07-01-2024 --- Yes
Application deemed complete (Agency Action) 07-31-2024 07-31-2024 01-31-2025 No
Final decision/agency action (Agency Action) 09-30-2024 09-30-2024 03-31-2025 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-01-2024 07-01-2024 --- Yes
Application deemed complete (Agency Action) 07-31-2024 07-31-2024 --- No
Final decision/agency action (Agency Action) 09-30-2024 09-30-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-01-2024 07-01-2024 --- No
Application deemed complete (Agency Action) 07-31-2024 07-31-2024 --- No
Final decision/agency action (Agency Action) 09-30-2024 09-30-2024 --- No