USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 02-23-2024 02-23-2024 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 10-15-2024 03-04-2025 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-13-2025 06-02-2025 --- No
Planned
  The project sponsor’s delayed submission of information needed for a complete Marine Mammal Protection Act (MMPA) Incidental Take Authorization (ITA) application has resulted in delays to the schedule for NMFS’s issuance of the proposed ITA as well as delays to the development of complete Endangered Species Act (ESA) and Essential Fish Habitat (EFH) consultation documents, the Draft Environmental Impact Statement (DEIS), the Final Environmental Impact Statement (FEIS) and all other subsequent dependent milestones. BOEM developed an updated permitting timetable reflecting the 90-day shift to the DEIS, FEIS, and Record of Decision (ROD) milestone dates. The NEPA Action is impacted by the milestone shifts for the ESA Action as a result of the shifts for the MMPA Action; the NEPA timeline is changing accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 02-23-2024 02-23-2024 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 10-15-2024 03-04-2025 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-13-2025 06-02-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 02-23-2024 02-23-2024 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 10-15-2024 10-15-2024 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-13-2025 01-13-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 02-23-2024 02-23-2024 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 10-15-2024 10-15-2024 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-13-2025 01-13-2025 --- No