Permitting Action Modification History
Modifications on 11/04/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 03-31-2026 | 03-31-2026 | 04-03-2026 | Yes |
| Scoping (Agency Action) | 03-31-2026 | 03-31-2026 | 04-03-2026 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 02-05-2027 | 02-05-2027 | 05-07-2027 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 11-12-2027 | 11-12-2027 | 12-15-2027 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 01-05-2028 | 01-05-2028 | --- | No |
Modifications on 04/03/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 03-31-2026 | 03-31-2026 | 04-03-2026 | Yes |
| Scoping (Agency Action) | 03-31-2026 | 03-31-2026 | 04-03-2026 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 02-05-2027 | 02-05-2027 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 11-12-2027 | 11-12-2027 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 01-05-2028 | 01-05-2028 | --- | No |
Modifications on 04/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 03-31-2026 | 03-31-2026 | 04-03-2026 | No |
| Scoping (Agency Action) | 03-31-2026 | 03-31-2026 | 04-03-2026 | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 02-05-2027 | 02-05-2027 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 11-12-2027 | 11-12-2027 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 01-05-2028 | 01-05-2028 | --- | No |
Modifications on 03/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 03-31-2026 | 03-31-2026 | --- | No |
| Scoping (Agency Action) | 03-31-2026 | 03-31-2026 | --- | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 02-05-2027 | 02-05-2027 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 11-12-2027 | 11-12-2027 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 01-05-2028 | 01-05-2028 | --- | No |