FAST-41 Missed Date:Environmental Impact Statement (EIS): Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 11/17/2025 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
Planned
POC Name:
Lea Garcia
POC Title:
Energy Development Project Manager
POC Email:

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
  • Monthly Status Report for July 2026:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities.
  • Monthly Status Report for June 2026:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities. 
  • Monthly Status Report for May 2026:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities. 
  • Monthly Status Report for April 2026:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. At that time, BLM notified the sponsor that the project’s funding had lapsed due to the sponsor’s lack of response to BLM’s prior request for additional funds.
  • Monthly Status Report for March 2026:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. After the cost recovery payment was processed, the BLM resumed work on the Notice of Deficiency and submitted it to the project sponsor. The BLM, as requested by the sponsor, is delaying additional processing steps until a response to the Notice of Deficiency is received. The BLM has updated the milestones and will continue to do work necessary to meet milestones or submit a request to update the project schedule.
  • Monthly Status Report for February 2026:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. After the cost recovery payment was processed, the BLM resumed work on the Notice of Deficiency and submitted it to the project sponsor. The BLM, as requested by the sponsor, is delaying additional processing steps until a response to the Notice of Deficiency is received. The BLM has updated the milestones and will continue to do work necessary to meet milestones or submit a request to update the project schedule.
  • Monthly Status Report for January 2026:
    The BLM continues to meet with the project sponsor on a regular basis. 
  • Monthly Status Report for December 2025:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities. 
  • Non-conformance Explanation:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. At that time, BLM notified the sponsor that the project’s funding had lapsed due to the sponsor’s lack of response to BLM’s prior request for additional funds. In accordance with 43 CFR 2804.19(d) and the terms of the project’s Cost Recovery Agreement, BLM cannot resume work on the application until sufficient funds are received. Although the sponsor indicated their intent to provide additional funding, the required funds to re-initiate work were not received until October 1, 2025. By that time, the BLM was initiating Government shutdown protocols, and the deadline for submitting a request to update FAST-41 milestones had already passed. BLM policy, as outlined in the H-1301-1 Fund Code Handbook, requires managers to ensure that employees do not continue work in sub-activities where funding is depleted or unavailable. Additionally, per the H-1372-1 Cost Recovery Handbook, funds must be deposited into cost recovery accounts before obligations are incurred. These policies are in place to ensure compliance with the Antideficiency Act, which prohibits federal agencies from incurring obligations in excess of available appropriations. Because the project funds were depleted and no additional funding sources were available at the time, BLM could not continue work necessary to meet milestones or submit a request to update the project schedule.
Current Target Date:
Scoping (Agency Action)
Current Target Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Milestone
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
  • Monthly Status Report for July 2026:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities.
  • Monthly Status Report for June 2026:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities. 
  • Monthly Status Report for May 2026:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities. 
  • Monthly Status Report for April 2026:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. At that time, BLM notified the sponsor that the project’s funding had lapsed due to the sponsor’s lack of response to BLM’s prior request for additional funds.
  • Monthly Status Report for March 2026:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. After the cost recovery payment was processed, the BLM resumed work on the Notice of Deficiency and submitted it to the project sponsor. The BLM, as requested by the sponsor, is delaying additional processing steps until a response to the Notice of Deficiency is received. The BLM has updated the milestones and will continue to do work necessary to meet milestones or submit a request to update the project schedule.
  • Monthly Status Report for February 2026:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. After the cost recovery payment was processed, the BLM resumed work on the Notice of Deficiency and submitted it to the project sponsor. The BLM, as requested by the sponsor, is delaying additional processing steps until a response to the Notice of Deficiency is received. The BLM has updated the milestones and will continue to do work necessary to meet milestones or submit a request to update the project schedule.
  • Monthly Status Report for January 2026:
    The BLM continues to meet with the project sponsor on a regular basis. 
  • Monthly Status Report for December 2025:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities. 
  • Non-conformance Explanation:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. At that time, BLM notified the sponsor that the project’s funding had lapsed due to the sponsor’s lack of response to BLM’s prior request for additional funds. In accordance with 43 CFR 2804.19(d) and the terms of the project’s Cost Recovery Agreement, BLM cannot resume work on the application until sufficient funds are received. Although the sponsor indicated their intent to provide additional funding, the required funds to re-initiate work were not received until October 1, 2025. By that time, the BLM was initiating Government shutdown protocols, and the deadline for submitting a request to update FAST-41 milestones had already passed. BLM policy, as outlined in the H-1301-1 Fund Code Handbook, requires managers to ensure that employees do not continue work in sub-activities where funding is depleted or unavailable. Additionally, per the H-1372-1 Cost Recovery Handbook, funds must be deposited into cost recovery accounts before obligations are incurred. These policies are in place to ensure compliance with the Antideficiency Act, which prohibits federal agencies from incurring obligations in excess of available appropriations. Because the project funds were depleted and no additional funding sources were available at the time, BLM could not continue work necessary to meet milestones or submit a request to update the project schedule.
Current Target Date:
Project

PROJECT WEBSITE: http://www.Clenera.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Description:

Bennett Solar B LLC proposes to construct, operate, maintain, and decommission a 240-megawatt (MW) solar photovoltaic (PV) power generating facility with a 960-MW hour (MWh) battery energy storage system.  The Project area is located approximately 6 miles east of Mountain Home, Idaho, and would be sited on approximately 2,122 acres of public land administered by the U.S. Bureau of Land Management (BLM).  The Project would also include a 230-kilovolt generation interconnection (gen-tie) line, PV module arrays, monitoring and maintenance facilities, electrical collector lines, and access roads.

field_status
System Comments
Agency Milestone Date of 11/17/2025 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
Approver Comments
<p><span style="-webkit-text-stroke-width:0px;background-color:rgb(255, 255, 255);color:rgb(0, 176, 80);display:inline !important;float:none;font-family:Arial;font-size:13.3333px;font-style:normal;font-variant-caps:normal;font-variant-ligatures:normal;font-weight:400;letter-spacing:normal;orphans:2;text-align:left;text-decoration-color:initial;text-decoration-style:initial;text-decoration-thickness:initial;text-indent:0px;text-transform:none;white-space:pre-wrap;widows:2;word-spacing:0px;">The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities.</span></p>
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
Agency Notified Date
New Milestone
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
  • Monthly Status Report for July 2026:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities.
  • Monthly Status Report for June 2026:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities. 
  • Monthly Status Report for May 2026:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities. 
  • Monthly Status Report for April 2026:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. At that time, BLM notified the sponsor that the project’s funding had lapsed due to the sponsor’s lack of response to BLM’s prior request for additional funds.
  • Monthly Status Report for March 2026:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. After the cost recovery payment was processed, the BLM resumed work on the Notice of Deficiency and submitted it to the project sponsor. The BLM, as requested by the sponsor, is delaying additional processing steps until a response to the Notice of Deficiency is received. The BLM has updated the milestones and will continue to do work necessary to meet milestones or submit a request to update the project schedule.
  • Monthly Status Report for February 2026:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. After the cost recovery payment was processed, the BLM resumed work on the Notice of Deficiency and submitted it to the project sponsor. The BLM, as requested by the sponsor, is delaying additional processing steps until a response to the Notice of Deficiency is received. The BLM has updated the milestones and will continue to do work necessary to meet milestones or submit a request to update the project schedule.
  • Monthly Status Report for January 2026:
    The BLM continues to meet with the project sponsor on a regular basis. 
  • Monthly Status Report for December 2025:
    The BLM continues to meet with the project sponsor on a regular basis regarding the project sponsor's July 12, 2025, decision to cease all processing activities. 
  • Non-conformance Explanation:
    On July 12, 2025, the project sponsor directed the BLM to cease all processing activities, while indicating that they did not wish to pause the FAST-41 process. At that time, BLM notified the sponsor that the project’s funding had lapsed due to the sponsor’s lack of response to BLM’s prior request for additional funds. In accordance with 43 CFR 2804.19(d) and the terms of the project’s Cost Recovery Agreement, BLM cannot resume work on the application until sufficient funds are received. Although the sponsor indicated their intent to provide additional funding, the required funds to re-initiate work were not received until October 1, 2025. By that time, the BLM was initiating Government shutdown protocols, and the deadline for submitting a request to update FAST-41 milestones had already passed. BLM policy, as outlined in the H-1301-1 Fund Code Handbook, requires managers to ensure that employees do not continue work in sub-activities where funding is depleted or unavailable. Additionally, per the H-1372-1 Cost Recovery Handbook, funds must be deposited into cost recovery accounts before obligations are incurred. These policies are in place to ensure compliance with the Antideficiency Act, which prohibits federal agencies from incurring obligations in excess of available appropriations. Because the project funds were depleted and no additional funding sources were available at the time, BLM could not continue work necessary to meet milestones or submit a request to update the project schedule.
Current Target Date:
Response Date
Reporting Agency