Permitting Action Modification History

In Progress
Completion date for EA process concluded changed to reflect shortening the timeline for the 106 review., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 06-26-2025 06-26-2025 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-15-2025 10-15-2025 02-19-2026 Yes
Issuance of a Final EA (Agency Action) 06-26-2026 06-26-2026 06-12-2026 Yes
EA Process Concluded (Agency Action) 04-28-2028 04-28-2028 01-25-2027 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 06-26-2025 06-26-2025 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-15-2025 10-15-2025 02-19-2026 Yes
Issuance of a Final EA (Agency Action) 06-26-2026 06-26-2026 06-12-2026 Yes
EA Process Concluded (Agency Action) 04-28-2028 04-28-2028 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 06-26-2025 06-26-2025 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-15-2025 10-15-2025 02-19-2026 Yes
Issuance of a Final EA (Agency Action) 06-26-2026 06-26-2026 --- No
EA Process Concluded (Agency Action) 04-28-2028 04-28-2028 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 06-26-2025 06-26-2025 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-15-2025 10-15-2025 --- No
Issuance of a Final EA (Agency Action) 06-26-2026 06-26-2026 --- No
EA Process Concluded (Agency Action) 04-28-2028 04-28-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 06-26-2025 06-26-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-15-2025 10-15-2025 --- No
Issuance of a Final EA (Agency Action) 06-26-2026 06-26-2026 --- No
EA Process Concluded (Agency Action) 04-28-2028 04-28-2028 --- No