Triggered missed date from extending FWS determines ESA Consultation Package is Complete - Formal (Agency Action) within 30 days of its current target date which was 04/04/2025 and extended to 10/08/2025
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/30/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Broadband
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Indian Affairs
View FAST-41 Postings by Agencies
Description:
The Gallup McKinley County School proposes to deploy a reliable, affordable, scalable, and future-proofed broadband network that bridges the digital divide for the foreseeable future in one of the most remote, isolated, high-cost, and difficult to serve areas of the United States. The Gallup McKinley County Schools E-Rate Funded Broadband Project consists of constructing approximately 65 miles of middle mile fiber optic network on the Navajo Nation to connect the school district with high-speed Internet connectivity to speeds of 1 Gbps or greater.