Permitting Action Modification History

In Progress
The primary driver of this timetable modification was to respond to the additional time requirement by the Project Sponsor to compile the necessary information for the BA to support the appropriate ESA consultation. Due to the size and complexity of the project, as well as the sensitivity of the ESA-listed species in the project area, it was necessary for the project sponsor to be as complete as possible with the project’s technical details. That required additional time to properly inform the USACE ESA determination and request forconsultation and FWS’s forthcoming BO., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-15-2025 01-15-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 05-13-2026 05-13-2026 --- Yes
ESA Consultation Concludes (Agency Action) 04-30-2026 09-25-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-15-2025 01-15-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 12-15-2025 05-13-2026 --- Yes
ESA Consultation Concludes (Agency Action) 04-30-2026 06-30-2026 --- No
Planned
Lead agency in cooperation with USFWS has deemed the BA submitted by the project proponent to be incomplete. A detailed document has been provided to both USACE and CTR citing the specific information requirements needed to complete the BA. Lead agency and USFWS are currently waiting on a estimated date of completion from CTR. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-15-2025 01-15-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 12-15-2025 05-13-2026 --- No
ESA Consultation Concludes (Agency Action) 04-30-2026 06-30-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-15-2025 01-15-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 12-15-2025 03-13-2026 --- No
ESA Consultation Concludes (Agency Action) 04-30-2026 06-30-2026 --- No
Planned
A delay via the project sponsor’s ability to provide the Biological Assessment(BA) to the lead agency (USACE) does not allow for enough time to conduct a thorough review and submit the BA draft to the FWS. As it stands the USACE is expected to receive the BA from the project sponsor's contractors on 1/15/26, this is the current target date for milestone one which means FWS would receive it concurrently with USACE. The USACE will need time to review and concur with the contents of the BA prior to submitting the official BA to FWS. Therefore, this milestone is being moved to allow for both agencies to complete their required reviews. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-15-2025 01-15-2026 --- No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 12-15-2025 03-13-2026 --- No
ESA Consultation Concludes (Agency Action) 04-30-2026 06-30-2026 --- No
Planned
The Applicant recently proposed changes to the project including construction of a new permanent access road, well pad, and injection well in an entirely new footprint, resulting in the loss of approximately 12 additional acres of aquatic resources. USACE must thoroughly evaluate and address the new activities, including the potential associated impacts on federally listed species, proposed compensatory mitigation, and evaluation of cultural and tribal resources. Additionally, since the Applicant substantially modified the reasonably foreseeable impacts to aquatic resources from those described in the original public notice, USACE determined a new public notice is necessary for proper evaluation of the proposal. To complete the public notice, USACE requested additional information required by regulation. The Applicant stated they will provide the information on November 5, 2025. Once received and determined complete, USACE will issue a public notice describing the modified proposal. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-15-2025 01-15-2026 --- No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 12-15-2025 02-15-2026 --- No
ESA Consultation Concludes (Agency Action) 04-30-2026 06-30-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-15-2025 11-15-2025 --- No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 12-15-2025 12-15-2025 --- No
ESA Consultation Concludes (Agency Action) 04-30-2026 04-30-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-15-2025 11-15-2025 --- No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 12-15-2025 12-15-2025 --- No
ESA Consultation Concludes (Agency Action) 04-30-2026 04-30-2026 --- No