USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Endangered Species Act Consultation (DOI-FWS): FWS determines ESA Consultation Package is Complete - Formal (Agency Action)

Submitted by lisa.landers@b… on

Triggered missed date from extending FWS determines ESA Consultation Package is Complete - Formal (Agency Action) within 30 days of its current target date which was 09/23/2022 and extended to 10/07/2022

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Eric Schrading
POC Title:
Fish and Wildlife Administrator

Description:

The Service will consult with BOEM on any project-related activities that may affect federally listed species or critical habitat.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
ESA Consultation Concludes (Agency Action)
  • Non-conformance Explanation:
    In a letter dated February 10, 2023, FWS stated that the collision risk posed by wind turbine generator operation is likely to adversely affect piping plover, rufa red knot, and roseate tern and that FWS is proceeding with formal consultation for these species effects. On February 13, 2023, and February 23, 2023, FWS notified BOEM via email that additional time is needed for FWS’s preparation of the draft Biological Opinion (BO), BOEM’s review of the draft BO, and FWS’s preparation of the final BO. Coordination between FWS and BOEM resulted in agreement that FWS would provide a draft BO on April 14, 2023, to BOEM for review, and BOEM would complete their review of the draft BO and provide FWS comments by April 26, 2023, and FWS would submit the final BO to BOEM by May 12, 2023.  Thus, BOEM and FWS requested to change the "ESA Consultation Concludes" milestone date from April 3, 2023 to May 12, 2023.  Since the final milestone is moving by more than 30-days, an Executive Director (ED) determination request was required.  The request to extend the final milestone date was submitted through an ED determination request on March 1, 2023, two days in advance of the FAST-41 30-day lockout period which began March 3, 3023.  However, even though the request was submitted two days before the 30-day lockout, the analysis and coordination required by the ED determination process could not be completed prior to the 30-day lockout period.  Therefore, the milestone went to nonconformance.
Alternative Completion Date:
05/12/2023
Milestone
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Ocean Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

9 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

Ocean Wind, LLC intends to construct, operate and maintain a commercial-scale offshore wind energy facility located approximately 15 miles off the coast of New Jersey within  Lease Area OCS-A 0498 (the “Ocean Wind 1 Project”). The Ocean Wind 1 Project, consisting of up to 98 wind turbine generators (WTG), inter-array cables, up to three Offshore Substations (OSS), two onshore substations, and two transmission cable routes making landfall in Ocean County, New Jersey and Cape May County, New Jersey,  is intended to fulfill the New Jersey Board of Public Utilities’ (BPU) September 20, 2018, solicitation for 1,100 MW of offshore wind capacity, and a corresponding Offshore Wind Renewable Energy Certificate (OREC) allowance of 4,851,489 MW-hours per year was awarded to Ocean Wind via BPU on June 21, 2019 (BPU Docket No. QO18121289, In the Matter of the Board of Public Utilities Offshore Wind Solicitation for 1,100 MW – Evaluation of the Offshore Wind Applications). The Ocean Wind 1 Project would contribute to New Jersey’s goal of 7.5 gigawatts (GW) of offshore wind energy generation by 2035 as outlined in New Jersey Governor’s Executive Order No. 92, issued on November 19, 2019. 

field_status
System Comments
Triggered missed date from extending FWS determines ESA Consultation Package is Complete - Formal (Agency Action) within 30 days of its current target date which was 09/23/2022 and extended to 10/07/2022
Approver Comments
30-day lockout should not start until 8/25/22.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
Yes
New Milestone
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
Response Date