Permitting Action Modification History
Modifications on 04/22/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 11-03-2025 | 11-03-2025 | --- | Yes |
| Completed application received (Applicant Action) | 12-03-2025 | 12-03-2025 | --- | Yes |
| Issuance of decision for permit/approval (Agency Action | 04-02-2026 | 01-18-2027 | --- | No |
Modifications on 02/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 11-03-2025 | 11-03-2025 | --- | No |
| Completed application received (Applicant Action) | 12-03-2025 | 12-03-2025 | --- | No |
| Issuance of decision for permit/approval (Agency Action | 04-02-2026 | 04-02-2026 | --- | No |
Modifications on 09/22/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 11-03-2025 | 11-03-2025 | --- | No |
| Completed application received (Applicant Action) | 12-03-2025 | 12-03-2025 | --- | No |
| Issuance of decision for permit/approval (Agency Action | 04-02-2026 | 04-02-2026 | --- | No |
Modifications on 09/26/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 11-03-2025 | 11-03-2025 | --- | No |
| Completed application received (Applicant Action) | 12-03-2025 | 12-03-2025 | --- | No |
| Issuance of decision for permit/approval (Agency Action | 04-02-2026 | 04-02-2026 | --- | No |