Triggered missed date from extending Issuance of Lead Agency Record of Decision within 30 days of its current target date which was 10/20/2021 and extended to 11/23/2021
Milestones:
-
Non-conformance Explanation:Missed Date Explanation (Published 10/21/2021): The 10/20/2021 completion date for "Issuance of Lead Agency Record of Decision" was missed because the Executive Director did not timely receive a request to modify the completion date. 42 U.S.C. 4370m-2(c)(2)(D)(i)(III) & (ii). Consultations under Section 106 of the National Historic Preservation Act are ongoing. Consulting parties requested additional time to review the Section 106 Memorandum of Agreement (MOA). The Record of Decision cannot be issued until the completion of the Section 106 process (i.e., execution of the MOA). In accordance with 42 U.S.C. 4370m-2(c)(2)(F)(ii), BOEM has established an alternative completion date of 11/23/2021.
-
Non-conformance Explanation:Missed Date Explanation (Published 10/21/2021): The 10/20/2021 completion date for "Issuance of Lead Agency Record of Decision" was missed because the Executive Director did not timely receive a request to modify the completion date. 42 U.S.C. 4370m-2(c)(2)(D)(i)(III) & (ii). Consultations under Section 106 of the National Historic Preservation Act are ongoing. Consulting parties requested additional time to review the Section 106 Memorandum of Agreement (MOA). The Record of Decision cannot be issued until the completion of the Section 106 process (i.e., execution of the MOA). In accordance with 42 U.S.C. 4370m-2(c)(2)(F)(ii), BOEM has established an alternative completion date of 11/23/2021.
PROJECT WEBSITE: South Fork Wind Farm - Deepwater Wind
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/18/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Environmental Protection Agency
Description:
The purpose of the South Fork Wind Farm (the Project) is to generate electricity from an offshore wind farm and transmit it to the existing East Hampton Substation, part of the Long Island Power Authority (LIPA) electric transmission and distribution system in East Hampton, New York. The Project addresses the need identified by LIPA for new sources of power generation that can cost-effectively and reliably supply the South Fork of Suffolk County, Long Island, as an alternative to constructing new transmission facilities. The Project will also help LIPA achieve its renewable energy goals. The Project will enable Deepwater South Fork to fulfill its contractual commitments to LIPA pursuant to a Power Purchase Agreement (PPA) executed in 2017 resulting from LIPA's technology-neutral competitive bidding process.
The South Fork Wind Farm is located in federal waters on the Outer Continental Shelf (OCS), specifically in Bureau of Ocean Energy Management (BOEM) Renewable Energy Lease Area OCS-A 0517, approximately 19 miles southeast of Block Island, Rhode Island, and approximately 35 miles east of Montauk Point, New York; The South Fork Export Cable is located on the OCS, in New York State Territorial Waters, and in the Town of East Hampton, New York.
Update:
The Executive Director granted a BOEM request to extend the final completion date for “Outer Continental Shelf (OCS) Air Permit,” “Issuance of final decision for permit/approval” until 01/18/2022. The Executive Director determination is available here.
-
Non-conformance Explanation:Missed Date Explanation (Published 10/21/2021): The 10/20/2021 completion date for "Issuance of Lead Agency Record of Decision" was missed because the Executive Director did not timely receive a request to modify the completion date. 42 U.S.C. 4370m-2(c)(2)(D)(i)(III) & (ii). Consultations under Section 106 of the National Historic Preservation Act are ongoing. Consulting parties requested additional time to review the Section 106 Memorandum of Agreement (MOA). The Record of Decision cannot be issued until the completion of the Section 106 process (i.e., execution of the MOA). In accordance with 42 U.S.C. 4370m-2(c)(2)(F)(ii), BOEM has established an alternative completion date of 11/23/2021.