EO 13807 Elevation Procedures for Date Extensions: Construction and Operations Plan

Submitted by amber.levofsky… on
Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Brian Krevor
POC Title:
NEPA Team Lead

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:

There are no milestones to display.

There are no milestones to display.

Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Ocean Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

9 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

OCW intends to develop, build, operate, and own (through one or more affiliated special purpose entities) a utility-scale offshore wind farm located approximately 15 miles off the coast of New Jersey within the Lease Area (the “Project”). The Project is being developed to serve the New Jersey market pursuant to the ongoing State of New Jersey’s Offshore Wind Economic Development Act Section 4 procurement process, administered by the New Jersey Board of Public Utilities (“NJBPU”). OCW was the sole beneficiary of New Jersey’s first 1,100 MW solicitation. Additional projects may also be developed within the Lease Area in the future in support of New Jersey Governor Phil Murphy’s Executive Order Number 8, which established a goal of developing 3.5 GW of offshore wind by 2030.1 Further solicitations by the NJBPU of 1,200 MW each are expected in 2020 and 2022.

field_status
System Comments
The following milestones have been extended 30 days past the current final target completion date for the following Action: Construction and Operations Plan

-Issuance of decision for permit/approval

The responsible agency of this Action, Department of the Interior Bureau of Ocean Energy Management, must indicate if Elevation Procedures were used for this extension.
Missed Date Process
No
Missed Date Triggered by Extension
No
Response Date
Original Milestone
Final decision/agency action (Agency Action)
Current Target Date: