Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-15-2019 08-15-2019 --- Yes
Application deemed complete (Agency Action) 10-01-2019 10-01-2019 --- Yes
Final decision/agency action (Agency Action) 06-29-2023 09-21-2023 --- Yes
In Progress
BOEM requests extension of the final Construction and Operations Plan (COP) milestone date to provide adequate time for BOEM to incorporate Coastal Zone Management Act federal consistency conditions, as well as measures issued as a result of the Endangered Species Act and Essential Fish Habitat consultations and developed through the Section 106 review, into the final Environmental Impact Statement, Record of Decision and COP decision. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 08-15-2019 08-15-2019 --- Yes
Application deemed complete (Agency Action) 10-01-2019 10-01-2019 --- Yes
Final decision/agency action (Agency Action) 06-29-2023 09-21-2023 --- No