Geothermal drilling permit means BLM written permission to drill for and test Federal geothermal resources. Belore a geothermal drilling permit can be approved, an operations plan must undergo NEPA review. Once approved, then geothermal drilling permit application(s) can be approved.
Geothermal Drilling Permit GDP
Permit/Review
Responsible Agency/Bureau
Project Type
Geothermal
Activity/Trigger
A lessee/operator proposing to apply for approval of drilling operations and well pad construction must submit geothermal drilling permit application(s) (Standard Form 3260-2) along with an operations plan, a complete drilling program, and an acceptable bond, 43 CFR 3261.11.
Description
Statute/Regulations
Geothermal Steam Act (30 USC 1001 et seq.); Federal Land Policy Management Act (43 USC 1701 et seq.); Energy Policy Act of 2005 (Pub. L. 109‐58); 43 CFR 3200.