Prior to the commercial generation of electricity, an application for a Commercial Use Permit is submitted and approved by BLM prior to any commercial operations from a Federal geothermal lease, a Federal Unit, or a production facility. This document describes the location of all wells, allocation of that production, location of meters, allocation of schedules, power purchase agreement, and a number of other items. It generally takes about a month for BLM approval of a Commercial Use Permit.
Commercial Use Permit
Permit/Review
Responsible Agency/Bureau
Project Type
Geothermal
Activity/Trigger
To initiate operations of a geothermal utilization facility, the lessee/operator must submit and receive approval of a commercial use permit.
Description
Statute/Regulations
Geothermal Steam Act (30 USC 1001 et seq.); Federal Land Policy and Management Act (43 USC 1701 et seq.); Energy Policy Act of 2005 (Pub. L. 109‐58); 43 CFR 3200.