Planned
FAST-41 Missed Date:Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation: NOAA Issues any EFH Conservation Recommendations (Agency Action)
Agency Milestone Date of 03/01/2023 for NOAA Issues any EFH Conservation Recommendations (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Endangered Species Act Consultation (DOI-FWS): ESA Consultation Concludes (Agency Action)
Triggered missed date from extending ESA Consultation Concludes (Agency Action) within 30 days of its current target date which was 03/31/2023 and extended to 05/14/2023
FAST-41 Missed Date:Section 408 Permit: Completeness Determination (Agency Action)
Triggered missed date from extending Completeness Determination (Agency Action) within 30 days of its current target date which was 03/24/2023 and extended to 04/26/2024
FAST-41 Missed Date:Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act: Publication of Public Notice (Agency Action)
Triggered missed date from extending Publication of Public Notice (Agency Action) within 30 days of its current target date which was 03/24/2023 and extended to 04/26/2024
FAST-41 Missed Date:Endangered Species Act Consultation (NOAA-NMFS): NOAA determines ESA Consultation Package is Complete - Formal (Agency Action)
Agency Milestone Date of 03/01/2023 for NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation: NOAA Issues any EFH Conservation Recommendations (Agency Action)
Agency Milestone Date of 03/01/2023 for NOAA Issues any EFH Conservation Recommendations (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Use Authorization (DOI-BOR): Application deemed complete (Agency Action)
Agency Milestone Date of 02/15/2023 for Application deemed complete (Agency Action) has passed by 1 business days