In Progress
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/30/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
FAST-41 Missed Date:Section 408 Permit: Issuance of Decision (Agency Action)
Agency Milestone Date of 02/02/2026 for Issuance of Decision (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Endangered Species Act Consultation (DOI-FWS): ESA Consultation Concludes (Agency Action)
Agency Milestone Date of 10/16/2025 for ESA Consultation Concludes (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Section 106 Review: Section 106 consultation concluded (Agency Action)
Agency Milestone Date of 11/03/2025 for Section 106 consultation concluded (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Environmental Impact Statement (EIS): Issuance of Lead Agency Record of Decision (Agency Action)
Agency Milestone Date of 11/03/2025 for Issuance of Lead Agency Record of Decision (Agency Action) has passed by 1 business days
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/30/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Texas