Paused
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Colorado
Description:
FAST-41 Missed Date: Endangered Species Act Consultation (DOI-FWS)
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 11/12/2019 and extended to 05/23/2021
FAST-41 Missed Date: Endangered Species Act Consultation (NOAA-NMFS)
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 01/24/2020 and extended to 07/08/2021
FAST-41 Missed Date: Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
Triggered missed date from extending NOAA Issues any EFH conservation recommendations within 30 days of its current target date which was 10/30/2019 and extended to 06/07/2021