USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date: Endangered Species Act Consultation (DOI-FWS)

Submitted by mary.boatman@b… on

Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 11/12/2019 and extended to 05/23/2021

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Status:
Paused
POC Name:
Tom
POC Title:
Chapman
POC Email:

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Current Target Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: South Fork Wind Farm - Deepwater Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/18/2022

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

The purpose of the South Fork Wind Farm (the Project) is to generate electricity from an offshore wind farm and transmit it to the existing East Hampton Substation, part of the Long Island Power Authority (LIPA) electric transmission and distribution system in East Hampton, New York. The Project addresses the need identified by LIPA for new sources of power generation that can cost-effectively and reliably supply the South Fork of Suffolk County, Long Island, as an alternative to constructing new transmission facilities. The Project will also help LIPA achieve its renewable energy goals. The Project will enable Deepwater South Fork to fulfill its contractual commitments to LIPA pursuant to a Power Purchase Agreement (PPA) executed in 2017 resulting from LIPA's technology-neutral competitive bidding process.

The South Fork Wind Farm is located in federal waters on the Outer Continental Shelf (OCS), specifially in Bureau of Ocean Energy Management (BOEM) Renewable Energy Lease Area OCS-A 0501, approximately 19 miles southeast of Block Island, Rhode Island, and approximately 35 miles east of Montauk Point, New York; The South Fork Export Cable is located on the OCS, in New York State Territorial Waters, and in the Town of East Hampton, New York.

field_status
System Comments
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 11/12/2019 and extended to 05/23/2021
Approver Comments
The missed milestone completion date or delay was attributable to reasons beyond the control of the agency.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
Yes
New Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Response Date