Cancelled
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY

LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
FAST-41 Missed Date:Section 408 Permit: Issuance of decision for permit/approval (Agency Action)
Final Required Milestone Date of 03/09/2021 for Issuance of decision for permit/approval (Agency Action) has passed by 5 business days
FAST-41 Missed Date:Section 408 Permit: Completeness determination (Agency Action)
Final Required Milestone Date of 01/08/2021 for Completeness determination (Agency Action) has passed by 5 business days
FAST-41 Missed Date: Special Use Permit (FS)
Final Required Milestone Date of 06/15/2022 for Issuance of decision for permit/approval has passed by 5 business days