US Coast Guard
FAST-41 Missed Date:USCG Bridge Permit: Application Deemed Complete (Agency Action)
Triggered missed date from extending Application Deemed Complete (Agency Action) within 30 days of its current target date which was 08/18/2025 and extended to 09/08/2025
FAST-41 Missed Date:USCG Bridge Permit: Publication of Public Notice (Agency Action)
Triggered missed date from extending Publication of Public Notice (Agency Action) within 30 days of its current target date which was 06/16/2025 and extended to 07/17/2025
FAST-41 Missed Date:USCG Bridge Permit: Issued Preliminary Navigation Clearance Determination (Agency Action)
Agency Milestone Date of 05/16/2025 for Issued Preliminary Navigation Clearance Determination (Agency Action) has passed by 1 business days