Project Name:
Responsible Agency:
Bureau of Land Management
Status:
Planned
Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
3506
-
Monthly Status Report for September 2026:BLM continues to engage DOI and the project sponsor on enhanced coordination and the administrative review of the Notice of Intent. The current target date for the NOI is October 14, 2026.
-
Non-conformance Explanation:The Bureau of Land Management (BLM) missed the August 12, 2026, milestone to publish the Notice of Intent to prepare an Environmental Impact Statement (EIS). The Notice of Intent for the Tonopah Flats Lithium Project has required enhanced coordination and administrative review at the Department of Interior (DOI) Headquarters and will be published once this is completed. Per 42 U.S.C.§ 4370m-2(c)(2)(F), BLM is providing October 14, 2026, as an alternative completion date and changes the scoping date to November 12, 2026.
Alternative Completion Date:
Scoping (Agency Action)
3511
Alternative Completion Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
3521
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
3536
Current Target Date: