Section 106 Review

Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
Complete
POC Name:
Chris Horrell
POC Title:
Marine Archaeologist
Action Outcome:
Executed memorandum of agreement or programmatic agreement or other conclusion to resolve adverse effects reached

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
  • Monthly Status Report for February 2024:
    BOEM is on track to meet the March 21, 2024 milestone. The Section 106 Memorandum of Agreement is with the consulting parties for a final review.
  • Monthly Status Report for January 2024:
    BOEM anticipates concluding Section 106 consultation on March 21, 2024 which is in alignment with the updated permitting timetable provided to the Permitting Council as part of an Executive Director Determination request in January of 2024.
  • Non-conformance Explanation:
    BOEM is undertaking a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompasses all agency actions and milestone dates for the project, including this action. BOEM anticipates providing by the end of December to the Permitting Council an updated time table for all actions, including this milestone.
Alternative Completion Date: