Project Name:
Responsible Agency:
Cooperating under NEPA
Bureau of Ocean Energy Management
Agency Status:
Cooperating under FAST-41Cooperating under NEPA
Status:
Complete
Action Outcome:
Notice to proceed
Description:
The final Construction and Operation Plan (COP) milestone is dependent on the NEPA schedule and will
shift in accordance with the ROD milestone shift.
Milestones:
Initial application submitted (Applicant Action)
4746
Completed Date:
Application deemed complete (Agency Action)
4751
Completed Date:
Final decision/agency action (Agency Action)
4756
-
Monthly Status Report for January 2025:The Record of Decision was published on 12/20/2024 and BOEM is on track to meet the COP milestone ahead of schedule.
-
Monthly Status Report for December 2024:The COP milestone is dependent on the NEPA action. For the NEPA Action, BOEM is on track to complete the ROD milestone on schedule.
-
Monthly Status Report for November 2024:The COP milestone is dependent on the NEPA action. For the NEPA Action, BOEM is on track to complete the ROD milestone on schedule.
-
Monthly Status Report for October 2024:The COP milestone is dependent on the NEPA action. For the NEPA Action, BOEM is on track to meet the next EIS milestone, publication of the FEIS NOA.
-
Monthly Status Report for September 2024:The COP milestone is dependent on the NEPA action. For the NEPA Action, BOEM is on track to meet the next EIS milestone, publication of the FEIS NOA.
-
Monthly Status Report for August 2024:The COP milestone is dependent on the NEPA action. For the NEPA Action, BOEM is on track to meet the FEIS milestone of November 15. BOEM received comment from the cooperators on the preliminary FEIS on Aug 19 and is reviewing their input.
-
Monthly Status Report for July 2024:The COP milestone is dependent on the NEPA action. For the NEPA action, the preliminary FEIS was sent to cooperating agencies in July for their initial round of review and BOEM expects to receive comments by Aug 19.
-
Monthly Status Report for June 2024:The COP milestone is dependent on the NEPA action. For the NEPA action, BOEM intends to distribute the preliminary FEIS to cooperating agencies in July, for initial review.
-
Monthly Status Report for May 2024:The COP milestone is dependent on the NEPA action. For the NEPA action, BOEM intends to distribute the preliminary FEIS to cooperating agencies in July, for initial review.
-
Monthly Status Report for April 2024:The COP milestone is dependent on the NEPA action. For the NEPA action, BOEM is working on responding to comments on the DEIS and preparing the preliminary FEIS.
-
Monthly Status Report for March 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM subsequently participated in 3 convening meetings with the Permitting Council and the Sponsor. BOEM is currently undertaking a final review of the revised permitting timetable to reset the schedule for the remaining milestones.
-
Non-conformance Explanation:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM subsequently participated in three convening meetings with the Permitting Council and the Sponsor and currently has a revised permitting timetable before the Permitting Council to reset the schedule for the remaining milestones.
Alternative Completion Date: