Permitting Action Modification History
Modifications on 01/17/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-15-2021 | 02-15-2021 | --- | Yes |
| Application deemed complete (Agency Action) | 05-27-2021 | 05-27-2021 | --- | Yes |
| Final decision/agency action (Agency Action) | 01-25-2024 | 01-25-2024 | 01-17-2025 | Yes |
Modifications on 04/08/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-15-2021 | 02-15-2021 | --- | Yes |
| Application deemed complete (Agency Action) | 05-27-2021 | 05-27-2021 | --- | Yes |
| Final decision/agency action (Agency Action) | 01-25-2024 | 01-25-2024 | 03-27-2025 | No |
Modifications on 11/30/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-15-2021 | 02-15-2021 | --- | Yes |
| Application deemed complete (Agency Action) | 05-27-2021 | 05-27-2021 | --- | Yes |
| Final decision/agency action (Agency Action) | 01-25-2024 | 01-25-2024 | --- | No |