Environmental Impact Statement (EIS)

Project Name: Responsible Agency:
Bureau of Land Management
Status:
Planned
POC Name:
Robbie McAboy
POC Title:
District Manager
POC Email:

Description:

Resource Management Plan Amendment and Environmental Impact Statement

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
  • Non-conformance Explanation:
    The DOI-BLM internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project.
Alternative Completion Date:
Scoping (Agency Action)
Alternative Completion Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Alternative Completion Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date: