Project Name:
Responsible Agency:
Fish and Wildlife Service
Agency Status:
Cooperating under FAST-41
Status:
Paused
Milestones:
ESA Consultation Request Package Submitted (Agency Action)
3811
-
Monthly Status Report for September 2025:In mid-March 2025, the BLM and FWS determined that a Biological Assessment needs to include Monarch Butterfly, Yuma Ridgway Rail, and CA Black Rail species prior to submission to FWS for review. Based on recommended survey protocols, the BA is planned to be completed by 2/13/2026. BLM continues to work with FWS to complete the BA.
-
Monthly Status Report for August 2025:In mid-March 2025, the BLM and FWS determined that a Biological Assessment needs to include Monarch Butterfly, Yuma Ridgway Rail, and CA Black Rail species prior to submission to FWS for review. Based on recommended survey protocols, the BA is planned to be completed by 2/13/2026.
-
Monthly Status Report for July 2025:In mid-March 2025, the BLM and FWS determined that a Biological Assessment needs to include Monarch Butterfly, Yuma Ridgway Rail, and CA Black Rail species prior to submission to FWS for review. Based on recommended survey protocols, the BA is planned to be completed by 2/13/2026.
-
Monthly Status Report for June 2025:In mid-March 2025, the BLM and FWS determined that a Biological Assessment needs to include Monarch Butterfly, Yuma Ridgway Rail, and CA Black Rail species prior to submission to FWS for review. Based on recommended survey protocols, the BA is planned to be completed by 2/13/2026.
-
Monthly Status Report for May 2025:In mid-March 2025, the BLM and FWS determined that a Biological Assessment needs to include Monarch Butterfly, Yuma Ridgway Rail, and CA Black Rail species prior to submission to FWS for review. Based on recommended survey protocols, the BA is planned to be completed by 2/13/2026.
-
Non-conformance Explanation:In mid-March 2025, the Bureau of Land Management (BLM), in coordination with U.S. Fish and Wildlife Service (FWS), determined that a complete Biological Assessment that included completed threatened and endangered species surveys for the Monarch Butterfly, Yuma Ridgway Rail, and CA Black Rail species was needed before the package could be submitted for FWS review. Based on recommended survey protocols, the BA is planned to be completed by 2/13/2026.
Alternative Completion Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
3816
Alternative Completion Date:
ESA Consultation Concludes (Agency Action)
3821
Alternative Completion Date: