Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-04-2025 05-02-2025 02-13-2026 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 05-02-2025 06-01-2025 03-16-2026 No
ESA Consultation Concludes (Agency Action) 10-03-2025 10-29-2025 08-12-2026 No
Planned
BLM requests this extension of the final milestone dates to allow sufficient time for review and incorporation of new information into consultation documents and environmental reviews. Surveys for additional species and resurveying for surveys that were determined to be inadequate are needed based on discussions between BLM and FWS. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-04-2025 05-02-2025 02-13-2026 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 05-02-2025 06-01-2025 03-16-2026 No
ESA Consultation Concludes (Agency Action) 10-03-2025 10-29-2025 08-12-2026 No
Planned
The BLM is awaiting reports (Biological, Cultural, and Water Supply Assessment) from the project sponsor. The project sponsor is also set to resubmit an updated plan of development (POD), version 10, for review in February. The project is anticipated to be extended by 29 days, which would give BLM adequate time to review the reports and POD. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-04-2025 05-02-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 05-02-2025 06-01-2025 --- No
ESA Consultation Concludes (Agency Action) 10-03-2025 10-29-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-04-2025 04-04-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 05-02-2025 05-02-2025 --- No
ESA Consultation Concludes (Agency Action) 10-03-2025 10-03-2025 --- No