Description:
This milestone is for a BOR Use Authorization for Phase II of the Navajo Nation Department of Education (NN DOE) project as assessed by the NN DOE Phase II Environmental Assessment. The proposed project would serve the 11 Navajo communities; starting with San Juan Chapter, Bloomfield to Counselor and Huerfano, Crownpoint, Lake Valley, White Rock, Becenti, Rock Springs, Bread Springs, Casamero Lake, Churchrock, Pinedale, Mariano Lake, and Pueblo Pintado.
Milestones:
-
Non-conformance Explanation:Reclamation continues to work with Sacred Wind and their team to finalize accurate construction drawings for the project required for Reclamation to deem the application complete. Reclamation sent comments on the last set of drawings received from the project sponsor's designee on 9/29. The comments were not extensive so Reclamation anticipates a few days for the designee will allow them sufficient time to prepare final accurate drawing allowing Reclamation to deem the application complete on 10/8.