Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation

Project Name: Responsible Agency:
National Oceanic and Atmospheric Administration
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Complete
POC Name:
Steve Giordano
POC Title:
Ecosystem Restoration and Environmental Compliance Program Manager
Action Outcome:
One or more EFH conservation recommendations are issued

Description:

Section 305(b)(2) of the Magnuson-Stevens Fishery Conservation and Management Act (MSA) requires federal agencies to consult with NOAA Fisheries on any action or proposed action that may adversely affect Essential Fish Habitat (EFH). EFH exists throughout the area affected by the proposed Mid-Barataria project. The proposed action may adversely affect these resources, therefore EFH consultation is required.  The final consultation completion date is contingent upon NOAA Fisheries receiving sufficient information to initiate EFH consultation.

Milestones:

EFH Consultation Request Submitted – EFH Assessment (Agency Action)
Completed Date:
Milestone Details

This is the date NOAA anticipates receiving a Draft EFH assessment, developed through multiple collaborative iterations with the state and action agency.  The ability to meet this target date is contingent upon receiving an EFH consultation request, including an EFH assessment by the date indicated.

NOAA determines EFH Assessment is Complete (Agency Action)
  • Environmental Impact Statement (EIS) : Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
    - Completed Date: 03/05/2021
Completed Date:
Milestone Details

This is the date NOAA anticipates receiving the Final EFH assessment. Consultation Initiation is contingent upon NMFS receiving sufficient information to initiate EFH consultation.

NOAA Issues any EFH Conservation Recommendations (Agency Action)
Completed Date:
Milestone Details

Issuance of Conservation Recommendations is contingent upon NMFS receiving sufficient information, including a sufficient EFH Assessment, to initiate EFH Consultation.