Permitting Action Modification History
Modifications on 08/31/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| EFH Consultation Request Submitted – EFH Assessment (Agency Action) | 02-24-2021 | 02-24-2021 | --- | Yes |
| NOAA determines EFH Assessment is Complete (Agency Action) | 04-07-2021 | 04-07-2021 | --- | Yes |
| NOAA Issues any EFH Conservation Recommendations (Agency Action) | 06-02-2021 | 05-04-2021 | --- | Yes |