Endangered Species Act Consultation (NOAA-NMFS)

Project Name: Document URL: Biological Opinion available on Environmental Consultation Organizer (ECO) site.
Responsible Agency:
National Oceanic and Atmospheric Administration
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Complete
POC Name:
Steve Giordano
POC Title:
Ecosystem Restoration and Environmental Compliance Program Manager
Action Outcome:
Biological opinion issued

Description:

Section 7(a)(2) of the Endangered Species Act (ESA) requires federal agencies to consult with NOAA Fisheries when any project or action they take might affect an ESA-listed species under NOAA Fisheries’ jurisdiction, or might affect such species’ critical habitat.  ESA-listed species and critical habitat exist throughout much of the area affected by the proposed Mid-Barataria project. The proposed action may affect these resources, therefore Section 7 consultation is required.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
  • Environmental Impact Statement (EIS) : Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
    - Completed Date: 03/05/2021
Completed Date:
Milestone Details

This is the date that NMFS anticipates receiving the Draft Biological Assessment (BA), developed through multiple collaborative iterations with the state and action agency. NMFS performs final review and determines sufficiency of BA.

 

NOAA determines ESA Consultation Package is Complete - Formal (Agency Action)
Completed Date:
Milestone Details

This is the date that NMFS anticipates receiving the Final BA with the request for formal consultation from the USACE. Consultation initiation is contingent upon NMFS receiving sufficient information to initiate ESA consultation.

 

ESA Consultation Concludes (Agency Action)
Completed Date:
Milestone Details

Final NLAA/Biological Opinion Issued. The final completion date is contingent upon NMFS receiving sufficient information to complete ESA consultation.