Permitting Action Modification History
Modifications on 08/31/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 02-12-2020 | 02-12-2020 | --- | Yes |
| NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) | 10-09-2020 | 02-24-2021 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 06-15-2021 | 12-13-2021 | --- | Yes |
Modifications on 05/04/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 02-12-2020 | 02-12-2020 | --- | Yes |
| NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) | 10-09-2020 | 02-24-2021 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 06-15-2021 | 12-13-2021 | --- | Yes |