Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Project Name: Document URL: Public Notice
Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Complete
POC Name:
Heather Markway
POC Title:
Project Manager
Public Participation Website:
Action Outcome:
Permit issued/verified

Description:

The proposed Hilcorp Alaska LLC Liberty Development project requires Federal Action (i.e., a permit) under three U.S. Army Corps of Engineers (USACE) regulatory authorities, in addition to Section 4(f) of OCSLA, which addresses construction of artificial islands on the seabed to the seaward limit of the outer continental shelf. USACE jurisdiction over an artificial island in OCS on “lands” under mineral lease from MMS (now BOEM) is limited to the evaluation of impacts to navigation and national security, 33 CFR 322.5 (f). 

Section 404 (b) of the Clean Water Act contains the guidelines for specification of disposal sites for dredged or fill material into waters of the United States (33 USC §§ 1344, 1362) (pipeline in territorial sea, gravel material site in wetlands, VSMs and gravel pads supporting pipeline construction in wetlands). In summary, dredge or fill material shall not be permitted if it violates any applicable State water quality standard; violates any applicable toxic effluent standard; jeopardizes the continued existence of species listed as threatened or endangered; or violates any marine sanctuary protection requirements.

Section 10 of the RHA (commonly referred to as the Rivers and Harbors Act) addresses the construction or modification of structures in navigable waters, or the accomplishment of any other work affecting the course, location, condition, or physical capacity of navigable waters (33 USC §§ 403).

Section 10 of the RHA would also apply to the construction of the pipeline in water on the OCS and in territorial seas. 

BOEM issued their final Record of Decision on October 22, 2018.  The Alaska District issued their final Record of Decision on February 8, 2019. 

 The signed permit was received on April 30, 2019 and countersigned on May 1, 2019. 

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Completed Date:
Milestone Details

The applicant submitted a complete application on June 30, 2017.

Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Completed Date:
Publication of Public Notice (Agency Action)
Completed Date:
Milestone Details

The Public Notice was issued on August 21, 2017 following the Official Notice of Availability of a Draft EIS was published in the Federal Register in order to align the public comment period of the application with the public review period of the DEIS.    

Final Verification/Permit Decision Rendered (Agency Action)
Completed Date:
Milestone Details

 The signed permit was received on April 30, 2019 and countersigned on May 1, 2019.