Permitting Action Modification History
Modifications on 03/29/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 06-18-2020 | 06-18-2020 | --- | Yes |
| Scoping (Agency Action) | 12-11-2020 | 12-11-2020 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 07-09-2021 | 07-09-2021 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 12-10-2021 | 12-10-2021 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 03-17-2022 | 03-17-2022 | --- | No |