Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-27-2022 11-18-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-26-2022 02-08-2023 --- Yes
ESA Consultation Concludes (Agency Action) 02-07-2023 05-24-2023 06-22-2023 Yes
In Progress
Milestone was extended to 6/26/23 because new information was received in a BA addendum on 3/28/23, and the USFWS requested more time to incorporate the new information into the Biological Opinion.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-27-2022 11-18-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-26-2022 02-08-2023 --- Yes
ESA Consultation Concludes (Agency Action) 02-07-2023 05-24-2023 06-26-2023 No
In Progress
BOEM’s request for an extension of the FWS ESA completion date is based on the need for the Project Sponsor to input data into the recently updated collision risk model for birds.  The model results will also need to be incorporated into BOEM’s biological assessment, which will then need to be resubmitted to FWS. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-27-2022 11-18-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-26-2022 02-08-2023 --- Yes
ESA Consultation Concludes (Agency Action) 02-07-2023 05-24-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-27-2022 11-18-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-26-2022 02-08-2023 --- Yes
ESA Consultation Concludes (Agency Action) 02-07-2023 04-24-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-27-2022 11-18-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-26-2022 02-08-2023 --- No
ESA Consultation Concludes (Agency Action) 02-07-2023 04-24-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-27-2022 11-18-2022 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-26-2022 02-08-2023 --- No
ESA Consultation Concludes (Agency Action) 02-07-2023 04-24-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-27-2022 06-27-2022 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-26-2022 08-26-2022 --- No
ESA Consultation Concludes (Agency Action) 02-07-2023 02-07-2023 --- No