Washington D.C. to Baltimore Loop Project

PROJECT WEBSITE: Washington DC to Baltimore Loop Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The Washington D.C. to Baltimore Loop Project is a project wholly funded by The Boring Company, where the Maryland Department of Transportation (MDOT) is the project sponsor, in coordination with the Federal Highway Administration (FHWA) acting as the lead Federal agency. The project consists of the construction of a set of parallel, twin underground tunnels through which will run automated electric vehicles. The proposed twin tunnels will run in parallel for approximately 35.3 miles beneath public right-of-way from Washington, D.C. to Baltimore, Maryland. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete