Washington D.C. to Baltimore Loop Project
PROJECT WEBSITE: Washington DC to Baltimore Loop Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
							ENVIRONMENTAL REVIEW AND PERMITTING STATUS
							PAUSED
						
																																				ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
															SUBJECT TO CHANGE
													
							ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
							COMPLETED
						
								SECTOR
								Surface Transportation
							
							CATEGORY
																						
								Project Category
              DOT Projects
																				
								LEAD AGENCY
																	Department of Transportation, Federal Highway Administration
															
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The Washington D.C. to Baltimore Loop Project is a project wholly funded by The Boring Company, where the Maryland Department of Transportation (MDOT) is the project sponsor, in coordination with the Federal Highway Administration (FHWA) acting as the lead Federal agency. The project consists of the construction of a set of parallel, twin underground tunnels through which will run automated electric vehicles. The proposed twin tunnels will run in parallel for approximately 35.3 miles beneath public right-of-way from Washington, D.C. to Baltimore, Maryland.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
 
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
 - Responsible Agency:
 - Bureau:
 - Action Status:
 - SHPO:
 - Action Identifier:
 - Action Outcome:
 
| Milestone | Original Target Date | Current Target Date | Milestone Complete | 
|---|