USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Boardman to Hemingway Transmission Line

PERMITTING DASHBOARD PROJECT POSTING DATE: JULY 06, 2017

PROJECT WEBSITE: Boardman To Hemingway Project Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/18/2017

8 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

No icon

Department of Defense, US Navy

Department of Agriculture

Department of Agriculture, US Forest Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Bureau of Reclamation

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

PacifiCorp, Bonneville Power Administration (BPA), and Idaho Power jointly propose to design, construct, operate and maintain a new 500 kilovolt, single-circuit electric transmission line from a proposed substation near Boardman, Oregon to the Hemingway Substation near Melba, Idaho. The 500kV line will span approximately 300 miles total, 88 miles on land managed by the Bureau of Land Management (BLM). The project would provide additional capacity for exchanging energy between the Pacific Northwest and the Intermountain West, depending on which region is experiencing the highest demand.

BLM received Idaho Power Company’s Boardman to Hemingway Transmission Line Project application and Plan of Development (POD) on Dec. 19, 2007.

In keeping with its mission and NEPA, BLM has established collaborative relationships with many Federal, State and local organizations to facilitate cooperative government reviews, ensure science-based decision-making, and prevent duplicative efforts. As part of this approach, BLM incorporates input from the public and affected local governments into the review process. BLM relies on this input to develop an Environmental Impact Statement (as required by 30 CFR 550.269) to support its decision-making process. Additional information, including NEPA documentation, can be found on the Boardman to Hemingway project page, http://boardmantohemingway.com.

 

Update:

The Executive Director granted a Bureau of Land Management (BLM) request to extend the ; Use Authorization (DOI-BOR) & Section 404 Clean Water Act (USACE) completion date on November 18, 2022. The Executive Director determination is posted here.

The Executive Director granted a Bureau of Land Management (BLM) request to extend the Use Authorization (DOI-BOR) & Section 404 Clean Water Act (USACE) completion date on April 14, 2023. The Executive Director determination is posted here.

The Executive Director granted a Bureau of Land Management (BLM) request to extend the Use Authorization (DOI-BOR) completion date on Feb 29, 2024. The Executive Director determination is posted here.

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete