USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

Submitted by carlos_arandia on

FWS received a complete and sufficient Biological Assessment on November 3, 2018 and anticipated concluding consultation within the 135 days provided by statute; however, due to a lapse in appropriations the government was shut down for 35 days. FWS anticipates concluding consultation by April 22, 2019, which allows for the entire 135 days provided by statute. Project sponsor is aware of the change. This should not affect any other timetables and all agencies are aware.

Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Cardinal-Hickory Creek 345 kV Transmission Line Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/06/2023

10 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Agriculture

LEAD AGENCY
Department of Agriculture, Rural Development

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

Dairyland Power Cooperative ("Dairyland"), a cooperative organized under the laws of Wisconsin, American Transmission Company LLC by its corporate
manager, ATC Management Inc., (together, "ATC"), and ITC Midwest LLC ("ITC Midwest") (all collectively, "Utilities") propose to construct and own the Cardinal— Hickory Creek Transmission Line Project ("Project"), a 345 kilovolt ("kV") transmission line connecting northeast Iowa and south-central Wisconsin.


The U.S. Department of Agriculture's Rural Utilities Service is currently the lead federal agency for the preparation of an Environmental Impact Statement for the Project. The U.S. Fish and Wildlife Service and the U.S. Army Corps of Engineers are Cooperating Agencies. As of 9/23/20, all of the permitting for the Project is complete.

field_status
System Comments
Furthest out Original Target Date: 11/16/2018
Milestone: Consultation Package Deemed Complete – Formal

Requested extensions greater than 30 days for this Action are shown below:

Conclusion of ESA Consultation by 157 days
From: 03/18/2019
To: 04/22/2019
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date: