1) Project sponsor (DCR Transmission, LLC) is not concerned with the delay because conclusion of the 106 process is not a critical path for project completion. Even with delay to 11/1/19 of 106 completion, record of decision on 11/22/19 will be maintained. 2) This change does not affect other aspects of permitting timetable, as stated above, record of decision date of 11/22/19 does not change. 3) Change was discussed with CERPO/Deputy CERPO on August status call and followed up on. 4) No time expected to be lost because this interim delay is not on the critical path for the project. Record of decision date of 11/22/19 remains the same. 5) CERPO/Deputy CERPO are aware of the delay in this milestone, they understand it should not affect project completion because it is an interim delay, not on the project critical path to record of decision.
PROJECT WEBSITE: Ten West Link Transmission Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/13/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Electricity Transmission
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of Transportation, Federal Aviation Administration
Description:
DCR Transmission, LLC (DCRT) filed a right-of-way (ROW) application (SF-299) with the Bureau of Land Management (BLM) on September 14, 2014, that proposes to construct, operate, maintain, and decommission an electric transmission project in western Arizona and eastern California. The proposed Ten West Link 500 kilovolt (kV) Transmission Line Project (the Project) would consist of a 500kV transmission line traversing approximately 114 miles. The Project would increase transmission capacity by 3,200 megawatts (MW) and provide interconnection capability for new energy projects located near the Project.
The Project would begin at the Arizona Public Service Company (APS) Delaney Substation near Tonopah, Arizona, and terminate at the Southern California Edison (SCE) Colorado River Substation near Blythe, California. The Project would be located in Maricopa and La Paz counties in Arizona, and Riverside County in California.
Milestone: Notification agency will use NEPA substitution approach [36 CFR 800.8(c)]
Requested extensions greater than 30 days for this Action are shown below:
Section 106 consultation concluded by 217 days
From: 07/29/2019
To: 11/01/2019