Milestone Extension: Endangered Species Act Consultation (DOI-FWS)

Submitted by carlos_arandia on

BLM issued its Draft EIS in August 2018; FWS received a complete and sufficient Biological Assessment on October 25, 2018 and anticipated concluding consultation within the 135 days provided by statute; however, due to a lapse in appropriations the government was shut down for 35 days.  FWS anticipates concluding consultation by April 15, 2019, which allows for the entire 135 days provided by statute.  BLM does not anticipate issuing its FEIS until May of 2019, and its ROD in July of 2019. Issuing the BO by April 15, 2019, will not delay any other project-related actions.

Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Bureau of Land Management Desert Quartzite Home Page

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/04/2020

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Project would be located approximately 2.75 miles southwest of the City of Blythe, just south of the Interstate 10 freeway, in Riverside County, California.  The Project involves construction of a 450 MW solar facility and a 3 mile long 230 kilovolt transmission line that would connect with Southern California Edison’s Colorado Substation.  After construction, the Project would occupy up to 2,673 acres of BLM land and 154 acres of private land under the jurisdiction of the County of Riverside. Once completed, the Project would also include an operations and maintenance building, an on-site substation, internal access roads, and ancillary facilities. 

field_status
System Comments
Furthest out Original Target Date: 03/11/2019
Milestone: Conclusion of ESA Consultation

Requested extensions greater than 30 days for this Action are shown below:

Conclusion of ESA Consultation by 35 days
From: 03/11/2019
To: 04/15/2019
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date: