USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Section 106 Review

Submitted by carlos_arandia on

Schedule back in progress, upon receipt of revised Plan of Development from proponent. Paused while waiting for revised POD, need for coordination with DRECP and California CEQA requirements. Additional minor delay occurred to coordinate with another FAST-41 project, solar Desert Quartzite, on that project's gen tie route.

Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Ten West Link Transmission Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/13/2022

5 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Transportation

Department of Transportation, Federal Aviation Administration

Description:

DCR Transmission, LLC (DCRT) filed a right-of-way (ROW) application (SF-299) with the Bureau of Land Management (BLM) on September 14, 2014, that proposes to construct, operate, maintain, and decommission an electric transmission project in western Arizona and eastern California. The proposed Ten West Link 500 kilovolt (kV) Transmission Line Project (the Project) would consist of a 500kV transmission line traversing approximately 114 miles. The Project would increase transmission capacity by 3,200 megawatts (MW) and provide interconnection capability for new energy projects located near the Project.

The Project would begin at the Arizona Public Service Company (APS) Delaney Substation near Tonopah, Arizona, and terminate at the Southern California Edison (SCE) Colorado River Substation near Blythe, California. The Project would be located in Maricopa and La Paz counties in Arizona, and Riverside County in California.

field_status
System Comments
Furthest out Original Target Date: 03/29/2019
Milestone: Notification agency will use NEPA substitution approach [36 CFR 800.8(c)]

Requested extensions greater than 30 days for this Action are shown below:

Section 106 consultation concluded by 122 days
From: 05/30/2019
To: 07/29/2019
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date: