Although the Corps is making every attempt to render a permit decision by June 22, 2019, a decision cannot be made until a mitigation plan is provided by the applicant that meets the requirements of 33 CFR 332. The Corps is reviewing the applicant's long-term management plan and financial assurances instrument for portions of the proposed permittee responsible mitigation areas. This information was provided by FPL on May 6, 2019, but the response did not include all of the necessary information. The Corps provided a template for guidance (Regulatory Guidance Letter 05-01) on financial assurances to FPL on May 8, 2019. FPL has not decided whether or not to use this example. As such, the Corps is requesting an extension of permitting timelines of the FPL Turkey Point project from June 22, 2019 until September 22, 2019. Should submittal of any required information be delayed, the Corps will need to continue to adjust its timeline.
PROJECT WEBSITE: http://www.nrc.gov/reactors/new-reactors/col/turkey-point.html
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/18/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Conventional Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Nuclear Regulatory Commission, Office of New Reactors
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Description:
The USACE proffered the remaining permit to the project sponsor (Florida Power and Light) December 18, 2019.
Florida Power and Light Company (FPL), seeks approval for constructing and operating two new AP1000 reactor units at the Turkey Point site to provide additional electricity for use in the Southern Florida service areas. The two new units would be capable of providing an additional 2200 megawatts of baseload electricity.
Milestone: Final Verification/Permit Decision Rendered
Requested extensions greater than 30 days for this Action are shown below:
Final Verification/Permit Decision Rendered by 335 days
From: 05/22/2019
To: 09/22/2019