USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Environmental Impact Statement (EIS)

Submitted by carlos_arandia on

NA

Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: E-Planning

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/29/2020

5 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The 690MW/ac Gemini Solar Project, once installed at full capacity, will be the largest solar photovoltaic (“PV”) project in the State of Nevada. The project site is located approximately 25 miles northeast of the Las Vegas metropolitan area, immediately south of the Moapa River Indian Reservation in an unincorporated area of Clark County, Nevada. Interstate 15 (I-15) is located less than ½ mile west of the project site. The NV Energy Crystal Substation and an NV Energy high-voltage transmission line are located less than four miles to the west.

field_status
System Comments
et Date: 09/12/2019
Milestone: Issuance of Record of Decision or combined Final EIS / Record of Decision

Requested extensions greater than 30 days for this Action are shown below:

Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review by 57 days
From: 08/21/2019
To: 11/08/2019

Issuance of Record of Decision or combined Final EIS / Record of Decision by 193 days
From: 09/25/2019
To: 03/23/2020
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date: