USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by carlos_arandia on

1. Project sponsor concurs with the date change. 2. A concurrent email is being sent to affected agencies but this date change does not affect other aspects of the permitting timetable. 3. The current CPP dated March 29, 2019 has a hyperlink to the Permitting Timetable where the revised target date will be displayed. This project has not been discussed at a CERPO meeting. 4. Possibly, depending upon when the Section 106 MOA is completed. 5. Yes.    
 

Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: http://penneastpipeline.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/27/2018

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

PennEast Pipeline (Docket No. CP15-558-000) would provide an additional 1.0 Bcf/d of natural gas transportation service through construction of:  (1) 115.1 miles of pipeline from Pennsylvania to New Jersey; (2) 2.1 miles of various lateral pipelines; and (3) a new compressor station.

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

Last updated March 27, 2021

field_status
System Comments
Furthest out Original Target Date: 12/01/2018
Milestone: Final Verification/Permit Decision Rendered

Requested extensions greater than 30 days for this Action are shown below:

Final Verification/Permit Decision Rendered by 303 days
From: 07/31/2019
To: 09/30/2019
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date: