USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by carlos_arandia on

This was previously approved by the Director and needs to be republished. From: Amber Levofsky - Y <amber.levofsky@gsa.gov> Sent: Wednesday, June 12, 2019 11:51 AM To: Giacinto, Joseph <Joseph.Giacinto@nrc.gov>; larry.burkhart@nrc.gov; Diaz Toro, Diana <Diana.Diaz-Toro@nrc.gov>; Kratchman, Jessica <Jessica.Kratchman@nrc.gov>; Erwin, Kenneth <Kenneth.Erwin@nrc.gov>; Klein, Amy S CIV USARMY USACE (US) <Amy.S.Klein@usace.army.mil>; Wingert, Sarah E CIV USARMY CEHQ (US) <Sarah.E.Wingert@usace.army.mil>; Haggerty, James W CIV USARMY CENAD (US) <James.W.Haggerty@usace.army.mil>; Chubb, Suzanne L CIV USARMY CELRD (US) <Suzanne.L.Chubb@usace.army.mil>; Scott.C.Kelly@usace.army.mil; Jason.W.Steele@usace.army.mil; Tonya.Acuff@usace.army.mil; Eakle, Wade L CIV USARMY CESPD (US) <Wade.L.Eakle@usace.army.mil>; Kate.M.Bliss@usace.army.mil; David W CIV USARMY CENWD (US) <David.W.Gesl@usace.army.mil>; Emily.K.Calla@usace.army.mil Cc: Fast Fortyone Operations <fastfortyone.operations@fpisc.gov>; Alexander Herrgott - Y <alexander.herrgott@fpisc.gov>; Karen Hanley - Y <karen.hanley@fpisc.gov>; Smith, Thomas P <Thomas.P.Smith@usace.army.mil>; Gaffneysmith, Margaret E CIV (US) <meg.e.gaffney-smith@usace.army.mil>; Taylor, Robert <Robert.Taylor@nrc.gov>; JENNIFER ADAMS - AY-C-D-C <jennifer.adams@gsa.gov> Subject: [External_Sender] Turkey Point Milestone Extension Request Approved Good morning , On behalf of the Executive Director, FPISC-OED has approved the following milestone extension request for Turkey Point, Units 6 and 7. The modified date is now available for you to review and then publish on the Permitting Dashboard. · Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act (USACE) o Final Verification/Permit Decision Rendered § Current published date: 5/22/2019 § New requested date: 9/22/2019 Please let us know if you have any questions or if there is anything else you would like to discuss. Sincerely,    
 

Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: http://www.nrc.gov/reactors/new-reactors/col/turkey-point.html

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/18/2019

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production

SECTOR
Conventional Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Nuclear Regulatory Commission

LEAD AGENCY
Nuclear Regulatory Commission, Office of New Reactors

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The USACE proffered the remaining permit to the project sponsor (Florida Power and Light) December 18, 2019.

Florida Power and Light Company (FPL), seeks approval for constructing and operating two new AP1000 reactor units at the Turkey Point site to provide additional electricity for use in the Southern Florida service areas.  The two new units would be capable of providing an additional 2200 megawatts of baseload electricity.

field_status
System Comments
Furthest out Original Target Date: 10/22/2018
Milestone: Final Verification/Permit Decision Rendered

Requested extensions greater than 30 days for this Action are shown below:

Final Verification/Permit Decision Rendered by 335 days
From: 05/22/2019
To: 09/22/2019
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date: