PROJECT WEBSITE: http://www.nrc.gov/reactors/new-reactors/col/turkey-point.html
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/18/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Conventional Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects

LEAD AGENCY
Nuclear Regulatory Commission, Office of New Reactors
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Description:
The USACE proffered the remaining permit to the project sponsor (Florida Power and Light) December 18, 2019.
Florida Power and Light Company (FPL), seeks approval for constructing and operating two new AP1000 reactor units at the Turkey Point site to provide additional electricity for use in the Southern Florida service areas. The two new units would be capable of providing an additional 2200 megawatts of baseload electricity.
Milestone: Final Verification/Permit Decision Rendered
Requested extensions greater than 30 days for this Action are shown below:
Final Verification/Permit Decision Rendered by 426 days
From: 09/22/2019
To: 12/22/2019